Districts Impacted
Rehabilitation work on several bridges over U.S. Route 54 is necessary to extend their lifespan and improve drivability and safety. Callaway County Route W, U.S. Route 63/Missouri Route 94, and Callaway County Route H/Business U.S. 54 bridges over U.S. Route 54 are in need of repairs.
U.S. Route 63/Route 94
Built in 1975, the twin bridges need deck repairs, concrete overlay, and application of protective coating. The guardrails on the Route 94 bridge will also be replaced.
The contractor will have up to 65 days on each of the twin bridges to complete the work. A signed detour will be in place. While some ramps will be closed, the eastbound U.S. Route 54 on-ramp to U.S. Route 63 will remain open. Neither bridge will be closed while the Route W bridge is under construction.
Route W
The 34-year-old Route W bridge over U.S. Route 54 will be closed for up to 60 days for deck repairs, concrete overlay, application of protective coating, and new guardrail installation.
A signed detour will be in place. Construction will not take place while the U.S. Route 63/Route 94 bridges are under rehabilitation.
Route H/Business U.S. 54
The Route H/Business U.S. 54 bridge, built in 1978, needs deck repairs, concrete overlay, and application of protective coating. Construction will close the bridge for up to 90 days and a signed detour will be in place.
The rehabilitation work will be started after construction crews complete the installation of offset left turn lanes at the intersection of U.S. Route 54 and Old Jefferson Road/County Road 306.
PROJECT PROGRESS
The Missouri Department of Transportation and its contractor designed improvements to extend the life of the bridges, including repairing the bridge decks, placing a latex concrete mix overlay, and applying a protective coating where necessary.
The Missouri Highways and Transportation Commission awarded a $24,463,380.36 contract to Magruder Paving, LLC to complete this project and three others (U.S. Route 54 eastbound expansion, U.S. Route 54 pavement resurfacing in Callaway County, and intersection improvements at U.S. Route 54 and Old Jefferson City Road).
Construction is anticipated to take place in 2024. Route W and Route H bridges will be fully closed, while one lane of U.S. Route 63/Route 94 bridges may be open. Signed detours will be in place.
Work on the bridges is expected to be completed by Dec. 1, 2024.
FREQUENTLY ASKED QUESTIONS
Why is MoDOT rehabilitating the bridges?
The planned work will extend the lifespan of the bridges and improve their drivability for motorists.
How will the bridge work affect traffic?
The contractor, working with MoDOT, will either fully or partially close each bridge for the duration of construction. Signed detours will be in place for each bridge while rehabilitation work is ongoing.
Who can I contact with further questions?
You may email cdcr@modot.mo.gov or call us at 888 ASK MODOT (1-888-275-6636). Please reference U.S. Route 63/Route 94, Route W, Route H over U.S. Route 54 Bridge Rehabilitations on your inquiries.
How can I stay updated on the project’s progress?
Sign up for project-specific updates using the form below.

PROJECT COORDINATION
This project is associated with the installation of offset left turn lanes at the intersection of U.S. Route 54 and Old Jefferson Road/County Road 306.
Other improvements to U.S. Route 54 in the vicinity include washing the bridges over the Missouri River, widening the eastbound traveled way, pavement improvements, and rehabilitation of the bridge over U.S. Route 50.